Here is the latest on the pool: The pool is just about ready, but we did find an air leak in one of the bottom pool pipes. All Aqua is looking into it. We had to replace the door next to the gym and the one at the employee lounge. Those should be arriving the first of next week and hopefully will be installed relatively quickly. The gate is being built. We’ve been told that it is supposed to be done on June 6, but we are hesitant to put a specific date out there because experience tells us that vendors don’t always live up to the dates they suggest. We filed the permit for the gate and we’re just waiting to hear back from the City. The slider door that leads out to the pool had to be replaced as well. This is all due to new code requirements. The door has to meet specific safety requirements which means we have two companies working on them — one to install the door and the other to wire the door to the fire alarm system. Everything is in place. We are just waiting on the permit and for the vendors to finish their work. We’ll keep you posted.