Owners,
We wanted to provide an update on the resort. According to our contract with the roofing company, they have 90 days to complete the work from the start of the contract, which is January 29. It appears they are ahead of schedule, which is great news. In fact, they can’t work today or tomorrow because of rain, but they said they will do their best to finish all of the cleanup on the roof and have their truck and crane out of the parking lot before Saturday (start of Bike Week).
US Glass is working on the basement level windows. They should be done in 3 weeks or fewer; however, their work is impacted by weather as well, and that is something that is clearly out of our control. Once they are done, the work on the pool can continue.